BIODEGRADABLE SOLID WASTE MANAGEMENT

Theory:

 

The Vertical Composting Unit (VCU) technology comprises of fully enclosed aerobic composting system that suits the processing of kitchen waste of small quantity. Composting takes place inside the modular chambers .The process is continuous with waste being loaded into the top of the chamber and stabilized material removed from the bottom.. The unique vertical orientation of the VCU processing chamber enhances a natural process, with aeration provided by fan mounted on top of each chamber. Odor control is by way of using a biofilter and leachate is not produced. The VCU offers low operating costs due to low energy, maintenance and labor costs it has a small footprint and offers great flexibility as it's modular design allows it to be easily expanded as collection systems are expanded and the volumes of waste are increased.

 

 

 

 

 

 

 

 

 

 

 

STANDARD COST OF ITEMS:

 

Quantity of waste = 75kg/day

 

Scope of supply of VERMIS  INDIA to Eastern ENVO:

 

Sr No

Item

Make

Qty

Cost(Rs.)

01

Screen for segregation of waste

Vermis India

01

 

02

Shredding machine

Vermis India

01

 

03

Vertical Composting Unit , MS vessel with FRP inside, with motorized augur, Ventilating Fan, Odor control Bio Filter, inlet door, outlet door, leachate collection pipe

Vermis India

01

 

04

Consultancy cum supervision, includes drawings for excluded items and travel

Vermis India

 

 

 

 

 

Total

 

 

Add Taxes

 

1.   SERVICE TAX: EXTRA will be charged as and when required           

      2.    T.D.S may kindly be deducted as source

 

 

EXCLUDES:

 

 

Excluded Items

 

01

Collection platform, B/W

 

02

Storage Room for prepared compost for 25 days with fresh air ventilation and odor control filters, B/W

 

03

Packaging Machine, weighing machine

 

04

Waste Water Treatment plant to Treat Lechate, 1 No

 

05

Boundary wall

 

06

Roads

 

 

Total cost of works

 

 

 

 

b} Variable Cost

C

Variable Cost

 

01

Carrying/transportation, processing

 

02

Packing Material

 

03

Labour charge@20.000/month

 

04

Advertise/leaflet/stationary

 

05

Office staff  @  20,000/month

Municipal Engineering Specialist

 

Agriculture Specialist

 

06

Fuel and Miscellaneous operating cost

 

 

Total variable cost

 

 

 

Payment terms:

 

Material supply:

 

40% advance alongwith work order

60% against proforma invoice before despatch

 

Consultancy:

 

60% as advance

30% after submission of all drawings

10% after erection and commissioning

 

 

For VERMIS INDIA

 

 

 

 

SYED RAKIB HUSSAIN

09899377953

 

Call me for any more informations required by you.